I.  Corrections to minutes from last meeting on September 25, 2006?  No.

 

II. Ongoing Discussion Topics:

  ( Click to review the agenda from this meeting )

*    “Condo” Cluster #2 – aka Dogwood: 

o        Update on configuration and rollout per Jim’s email of September 17:  Having some disk failures and Cisco switch performance issues.  After the recent power outage, the majority of nodes came back up on their own. Bill P will get with Networks person (Tang or Keith) to help determine what's going on with Cisco switch. Might keep just head node up next time power down system.

o        Any word from Mitch or SEAS faculty that wanted nodes or Infiniband cluster? No word yet.

o         HS faculty may purchase 8-16 of the existing nodes when he gets here; Tom S talking with Bill Woolfolk about Steve Rich's request

o        Steven de Wakker (EnviSci faculty) is here, still interested, ETF funds for this year.

*   Cedar Cluster: 

o        Avaki gateway setup – new software version released yet? Not heard anything yet.

o        64-bit test cluster?  Bill needs to use this for other testing right now.

o        Disk drive is failing in the head node – will contact HP.

*   Aspen & Birch Clusters: 

o        Aspen retired week of October 16 – turned off and will be surplussed. Under ETF until Summer 2007.

o        Other issues/concerns?  Watson (a Sun with large RAM) is being replaced – any interest? – could be available in a couple of weeks.  TimT will check on Athena use.

*   Oak Cluster:  Did the round-robin login get enabled? (Tim T. checked with Chip – no word back yet.)

*   Teak Cluster:  Any issues or concerns?

o        Do we need to set a “retirement” date for this equipment (which is hardly used)?  Still have the Gaussian licensing issues – we do have Gaussian98 recompiled and working on linux clusters – but only have binary for Gaussian03 so it can only run on Teak – and there are big! licensing issues with the vendor.  TimT will check on this.

*   Andrew Grimshaw’s request for Linux front-end to campus grid project – still waiting on next version of AVAKI.

o        Are all clusters now running Marty Humphrey’s Globus gatekeeper client that does direct file transfers?  No – but it’s on Steve’s list.

*   Proposal for Linux cluster support as ‘for-fee’ service.  Hamp has done a table of cost for supporting clusters (http://www.itc.virginia.edu/unixsys/support.html#hpcc).  Not really pushing this service as we’d prefer to encourage condo cluster participation.

*   Any update on conversion to authenticate to Eservices via Kerberos for Unix logins/connections to blue.unix, HSM, & Longtmp (AKA Phase 2 of the NetBadge CDP)?  No.

o        This transition will involve a major user education issue – especially for blue.unix users.

o        No timeline for this project yet – it has to wait until the password synchronization web site is up. 

o        ftp to blue.unix is being phased out, ITC  Service Transitions CDP working on schedule.

*   Mitch Rosen’s IT – Infrastructure Supporting Research Task Force.  (https://www1.seas.virginia.edu/itrtf).  (Maillist is itrtf@virginia.edu)  Final draft is circulating for input.  Katherine is doing the final editing.  Ed did most of the appendices that detail comparisons to other institutions.  Expect that we will be moving forward with something close to the Task Force recommendations – in phases.

o        CI-Team NSF proposal funded!  Course has a time and course number (CS494 Computational Mathematics) for spring07.  TimT will check with Andrew about the inclusion of Biology-related topics/students in this curriculum.

o        UVa’s participation in ORNL’s response to NSF RFP for next generation/iteration of Supercomputing Centers:  our partnership’s preliminary proposal was approved; the full proposal is due on 2/2/07.

*   “Priority” access for participants in condo clusters:  Katherine’s proposal for PBS “Service Units.”

o        Discussed other alternatives.  Need more information.

o        Will have this topic on next month’s agenda.

*   Update on longtmp and HSM upgrades: HSM delayed until next semester; Steve is working on longtmp.

 

III. New Business

*        Is it time to de-commission the “itc-rescomp” mail list?  Not for now – will continue to use it selectively.

*        Should we be responding to the SURA survey that went to Ariel?  It would definitely take some effort.  TimT will check with Ariel to see if it’s important to do this.

 

Next Scheduled Meeting of ITC ResComp Management team: Monday, November 27, 2006, 10:30 AM in ITC-2015 Ivy Road, Room #220. 

  =====================